1 Qs · 2011 · 1 marks · 0.1 marks/paperStandard yield
Software Estimation & Cost Models questions in GATE focus on the empirical calculation of project metrics such as development effort using parametric estimation models. Items requi… Guide
Topic guide
Software Estimation & Cost Models questions in GATE focus on the empirical calculation of project metrics such as development effort using parametric estimation models. Items require direct application of the Basic Constructive Cost Model (COCOMO) formula given project size and model coefficients.
Basic COCOMO Effort Computation
rare · MCQ · 1 marks · 2011
Given the estimated size in lines of code (LOC or KLOC) and the model coefficients (multiplicative factor and exponent for a specific project mode such as organic, semidetached, or embedded), calculate the total effort required in person-months.
Basic COCOMO Effort Formula
Used to compute software development effort in person-months given size in KLOC and empirical coefficients and .
Direct, single-step numerical substitution into empirical software estimation models (such as COCOMO) appeared as a standard 1-mark evaluation question.
2011
Easy items involve direct substitution into the basic effort formula with all coefficients provided. Medium to Hard items involve computing secondary metrics like development time (), average staffing size, or converting between function points and LOC before estimating effort.