A company needs to develop digital signal processing software for one of its newest inventions. The software is expected to have 40000 lines of code. The company needs to determine the effort in person-months needed to develop this software using the basic COCOMO model. The multiplicative factor for this model is given as 2.8 for the software development on embedded systems, while the exponentiation factor is given as 1.20. What is the estimated effort in person -months?

Select one answerSingle correct

Pick an option to check

Solution

Step-by-step verified solution

Official answer: A) 234.25

Software Estimation and Cost Models

According to the basic COCOMO model, the effort equation is:

Effort=a×(KLOC)b\text{Effort} = a \times (\text{KLOC})^b

Given:

  • Lines of code=40000  ⟹  KLOC=400001000=40\text{Lines of code} = 40000 \implies \text{KLOC} = \frac{40000}{1000} = 40

  • Multiplicative factor a=2.8a = 2.8

  • Exponentiation factor b=1.20b = 1.20

Substitute the values into the formula:

Effort=2.8×(40)1.20\text{Effort} = 2.8 \times (40)^{1.20}

Calculating (40)1.20(40)^{1.20}:

(40)1.20≈83.651(40)^{1.20} \approx 83.651
Effort=2.8×83.651≈234.22 person-months\text{Effort} = 2.8 \times 83.651 \approx 234.22 \text{ person-months}

Hence, the estimated effort is approximately 234.25 person-months, which matches option (A).

Try the question first, then check your work.

Think the official key or this write-up is wrong?

Report error or challenge

Examiner trap

The misconception this question tests

This Software Estimation and Cost Models previous year question is Q7 of the GATE CSE 2011 paper. Find more GATE CSE PYQs on Software Estimation and Cost Models in Software Engineering, or browse all GATE CSE PYQs.

Free diagnostic

Where do you stand for GATE?

Take the 20-minute diagnostic: the 3 topics that cost you the most marks, and a rank range. Or sit 1 related Software Estimation and Cost Models PYQs now with no account.

One GATE CSE PYQ every morning

An official question by email at 7 AM IST, with a link to its verified solution. Unsubscribe in one click.

Software Estimation and Cost Models in GATE CSE

GATE CSE 2011 Q7 is the only Software Estimation and Cost Models question in the GATE CSE papers so far.

How GATE tests Software Estimation and Cost Models

More from GATE CSE 2011

Share this solution

A plain-text card for WhatsApp or Telegram study groups.

GateAI solution cardGATE CSE 2011 · Q7 · MCQ

A company needs to develop digital signal processing software for one of its newest inventions. The software is expected to have 40000 lines of code. The company needs to determine the effort in person-months needed to develop this software using the basic COCOMO model. The multiplicative factor for this model is given as 2.8 for the software development on embedded systems, while the exponentiation factor is given as 1.20. What is the estimated effort in person -months?

Topic-wise GATE CS PYQs with verified steps

Independent practice explanation verified by the GateAI team. GATE is conducted by the IITs; question text follows the official paper.