Consider the following statements regarding the slow start phase of the TCP congestion control algorithm. Note that cwndcwnd stands for the TCP congestion window and MSS denotes the Maximum Segment Size. (i) The cwndcwnd increases by 2 MSS on every successful acknowledgment. (ii) The cwndcwnd approximately doubles on every successful acknowledgement. (iii) The cwndcwnd increases by 1 MSS every round trip time. (iv) The cwndcwnd approximately doubles every round trip time. Which one of the following is correct?

Select one answerSingle correct

Pick an option to check

Solution

Step-by-step verified solution

Official answer: C) Only (iv) is true

TCP Flow and Congestion Control

During the Slow Start phase of TCP congestion control:

  1. For every successful acknowledgment (ACK) received, the congestion window (cwndcwnd) increases by 1 MSS1\text{ MSS} (cwnd=cwnd+1 MSScwnd = cwnd + 1\text{ MSS}).

  2. Since the sender transmits an entire window of packets per round trip time (RTT) and each acknowledged packet increments cwndcwnd by 1 MSS1\text{ MSS}, the value of cwndcwnd approximately doubles every round trip time (RTT) (exponential growth).

Evaluating the given statements:

  • (i) is false because cwndcwnd increases by 1 MSS1\text{ MSS} per ACK, not 2 MSS2\text{ MSS}.

  • (ii) is false because cwndcwnd increases additively by 1 MSS1\text{ MSS} per ACK, not doubling per ACK.

  • (iii) is false because cwndcwnd increasing by 1 MSS1\text{ MSS} per RTT is the behavior of the Congestion Avoidance phase (Additive Increase), not Slow Start.

  • (iv) is true because exponential growth results in cwndcwnd doubling every RTT.

Hence, Only (iv) is true, which corresponds to option (C).

Try the question first, then check your work.

Think the official key or this write-up is wrong?

Report error or challenge

Examiner trap

The misconception this question tests

This TCP Flow and Congestion Control previous year question is Q14 of the GATE CSE 2018 paper. Find more GATE CSE PYQs on TCP Flow and Congestion Control in Computer Networks, or browse all GATE CSE PYQs.

Free diagnostic

Where do you stand for GATE?

Take the 20-minute diagnostic: the 3 topics that cost you the most marks, and a rank range. Or sit 5 related TCP Flow and Congestion Control PYQs now with no account.

One GATE CSE PYQ every morning

An official question by email at 7 AM IST, with a link to its verified solution. Unsubscribe in one click.

TCP Flow and Congestion Control in GATE CSE

TCP Flow and Congestion Control has 23 GATE CSE PYQs across 21 papers from 2012 to 2026. 10 of them are 1-mark MCQs like this one, and GATE CSE 2018 has 2.

How GATE tests TCP Flow and Congestion Control

More from GATE CSE 2018

Share this solution

A plain-text card for WhatsApp or Telegram study groups.

GateAI solution cardGATE CSE 2018 · Q14 · MCQ

Consider the following statements regarding the slow start phase of the TCP congestion control algorithm. Note that cwnd stands for the TCP congestion window and MSS denotes the Maximum Segment Size. (i) The cwnd increases by 2 MSS on every successful acknowledgment. (ii) The cwnd approximately doubles on every successful acknowledgement. (iii) The cwnd increases by 1 MSS every round trip time. (iv) The cwnd approximately doubles every round trip time. Which one of the following is correct?

Topic-wise GATE CS PYQs with verified steps

Independent practice explanation verified by the GateAI team. GATE is conducted by the IITs; question text follows the official paper.